The big news is that the Deloitte branch of our team has begun building the first version of UVA's tenant of Workday Financials! Wow!
The Configure & Prototype phase starts in November and will continue through March 2021 (check out our Phase 3 timeline). As we continue to move toward this major phase of the project, remember that change itself also involves phases. Read more about the change process so you can better understand the uncertainty we necessarily go through to reach a transformed future state.
Budget Team:
Functional Team:
Reporting and Analytics:
Technical Team
Budget Team:
- The discussion continues re: non-financial plan types: Awards, Projects
- Session held to continue review user story development
Functional Team:
- Lots of work on configuration workbooks and meetings with stakeholder groups are in progress
- System Remediation Network will begin meeting this fall. Read more here.
- See the latest decisions made here.
Reporting and Analytics:
- Reviewed reporting user stories for Grants Management based on reports list provided by the Office of Sponsored Programs
- Collected reporting requirements/user stories for Spend
Technical Team
- The COA to FDM mapping approach completion date will be delayed by two or more weeks. Read more on the latest with FDM here.
- Continued data scope analysis for suppliers and sub-recipients conversions
Adaptive Team
- Prepping for the FY22 budget process and gathering stakeholder feedback from the FY21R process.
- Read more about their current efforts.
Leadership Feedback
Want to know what folks around Grounds are saying about the project so far? Check out this roundup of thoughts from our recent Leadership Interviews!
No comments:
Post a Comment